Ibadan-Ife-Ilesa Road: Contractor resumes work after compliance with minister’s orders

CBC Global Civil and Building Construction Nigeria Limited says it has complied with directives issued by the Minister of Works, David Umahi, on improving the quality of work on the Ibadan-Ife-Ilesa Road and has resumed the reconstruction.
Its Area Manager, Yuan Kaizhi, disclosed this on Friday when he spoke with newsmen at the project site in Ikire, Osun State.
Kaizhi said all recommendations and corrections highlighted by the minister had been implemented, leading to the resumption of work.
The News Agency of Nigeria (NAN) reports that Umahi on June 21, 2026 directed the contractor to suspend work and review pavement mixture specifications at another project site before resuming.
The minister had also faulted the issuance of a N2.8 billion palliative certificate despite no palliative work being carried out, ordering the state Controller of Works to withdraw the certificate within 24 hours.
He further directed the contractor to undertake genuine palliative repairs, slow down work on the carriageway, and deploy two teams to simultaneously handle the inner and outer shoulders.
Providing an update, Kaizhi said the company had addressed all concerns raised during the minister’s inspection on June 21.
He said: “The minister made recommendations on the concrete mixture and the maintenance of the existing road.
“Following his directive, we visited another project site with engineers from the Federal Ministry of Works to study concrete preparation and on-site operations.
“On return, we immediately adjusted our mixture.
“As you can see, the changes have been implemented and the quality has improved.
“I can assure you that the road will last at least 50 years.”
On road maintenance, Kaizhi said palliative works had been carried out on the alternative lane to ease traffic flow.
He said: “We filled major potholes, applied a cement-stabilised base course, and laid asphalt.
“The road is now smoother, safer, and more convenient for motorists.”
The Project Manager, Anjikwi Anjilibwala, also confirmed compliance with the minister’s directives, noting that corrective measures on both the concrete mixture and palliative works had been completed.
He said the 108.4km project carries a 50-year durability guarantee, adding that about 65 percent of the current lane under construction had been completed.
Anjikibwala commended the minister for his intervention and expressed confidence that the project would meet required standards.
He noted that the project has a three-year completion timeline.
Some residents of the area commended President Bola Ahmed Tinubu for approving the reconstruction.
A resident, Ridwan Olabanji, said the project would bring significant relief and economic benefits to the community, while praising the minister for ensuring quality delivery.
Another resident, Oladimeji Ibrahim, also lauded the initiative and urged timely completion, commending the contractor for the pace and standard of work.
See Complete Details,Videos Here..
Society2 days agoIyabo Obasanjo clarifies father’s real age
Society2 days agoOutrage As Video Of Primary Schoolgirls Smoking And Drinking Surfaces Online
Breaking3 days agoNigerian nun in tears as she’s released after being arrested by ICE while walking to Mass in the US (video)
Breaking2 days ago"I would have contacted HIV or Hepatitis B if I had stayed" – Nigerian woman says as she reflects on her failed marriage
Investigation2 days agoEight de@d and 13 injured after being hit by truck ‘being driven by child’
Breaking2 days agoPanelists and guests on a podcast burst into laughter after 54-year-old US woman âmarriedâ to a 36-year-old Nigeria-based man, who she sends money to every month, laments about lack of love from him
World2 days agoMonaco bombing: Ukrainian oligarch's alleged mistress loses both legs as wife speaks out
Investigation2 days agoâ15k from someone in the US who promised me âbig moneyâ feels somehowâ â X user sparks debate